How to plan a renovation budget (and stick to it)
Updated 10 November 2026
Most renovations go over budget for the same few reasons: the estimate was one big number, nobody kept track of the small purchases, and there was no money set aside for what's behind the wall. Here's a simple way to avoid all three.
1. Break the project into rooms and parts
"Kitchen: 150,000" isn't a budget, it's a hope. Split it into the parts that have their own price: demolition, electrics, plumbing, cabinets, worktop, appliances, flooring, paint, and labour for each. Small lines are easy to price and easy to check later.
If several rooms are involved, budget each room separately. You'll see straight away which one is growing.
2. Get real prices, not guesses
- Get at least two quotes for any work you're hiring out, and check what's included (removal of rubbish, materials, VAT).
- Price materials from an actual store basket, not from memory.
- Add delivery, tool hire and skip rental – they're easy to forget and add up fast.
3. Add a contingency – 10 to 20 percent
Old houses hide things: rot under the floor, wiring that isn't up to code, a pipe that has to move. Put 10 % on top for a newer house and a simple job, 15–20 % for an older house or anything that opens walls or floors. Keep it as its own line so you can see when you start eating into it.
| Example: bathroom | Planned |
|---|---|
| Demolition & waterproofing | 22,000 |
| Plumbing (labour + parts) | 28,000 |
| Tiles & adhesive | 18,000 |
| Fixtures (toilet, basin, shower) | 21,000 |
| Electrics & lighting | 9,000 |
| Contingency 15 % | 14,700 |
| Total | 112,700 |
4. Record every expense as it happens
Budgets don't fail on the big invoices – those you remember. They fail on the twenty trips to the hardware store. The fix is boring but it works: log the expense and photograph the receipt at the till, not "later". Receipts printed on thermal paper fade within a few years anyway.
5. Compare planned and spent every week
Once a week, look at planned vs. spent for each part. If one line is over, decide right away: cut something elsewhere, use the contingency, or accept a higher total. Catching it early is the whole point.
6. Keep the record when you're done
When the project is finished, don't throw the numbers away. What it cost, when it was done, which products you used and the receipts are worth a lot later: for warranty claims, for insurance, for the next renovation estimate, and when you sell the house.